We have Shell and tube heat exchanger named E-201-11. This E-201-11 is exchanger just before pass heater of furnace of CDU. The service fluid is desalted crude (shell) and vacuum residue (tube) from bottom column.
Shell operating pressure is 19.7 kg/cm2 and tube operating pressere is 25.8 kg/cm2.
Pressure desain shell 30 kg/cm2 and pressure desain tube 36 kg/cm2.
Hydrotest pressure shell 43.5 and tube 37.5 kg/cm2.

What the main consideration of installing TSV at outlet of desalted crude?

Now, we are installing spare exchanger for E-201-11 but the type is plate and frame HE.
The operation mode will be one HE operated and one HE spare/stadby.

My question is : Do we need to install relief valve at desalted crude outlet of new HE?